The 35-kilometer Chandpur-Shariatpur four-lane road project has remained stalled for five years due to financial shortages, land acquisition complications, and administrative paralysis. Approved in the 2019–2020 fiscal year with a budget of Tk 860 crore, the project aimed to expand the road from Shariatpur’s Monohar Bazar to Vedarganj’s Ibrahimpur. Only six kilometers of work have been completed, leaving 29 kilometers unfinished and causing severe suffering for residents across 21 southern and southwestern districts.

According to the Roads and Highways Department (RHD), Tk 431.68 crore was allocated for acquiring 95.85 hectares of land, but Tk 430.29 crore was spent acquiring only 49 hectares. The remaining 46.85 hectares require an additional Tk 300 crore, which was not included in the original budget. Many landowners have received only acquisition notices without compensation, leaving them unable to sell or repair their properties.

Officials said the project’s tenure has been extended three times, with the current term ending on December 31, 2025. The RHD has requested another extension and a revision of the Development Project Proposal (DPP) to secure additional funds and restart the tendering process.

Card image

News Source

Amar Desh 27 Dec 25

দক্ষিণ-পশ্চিমাঞ্চলের ২১ জেলার মানুষ চরম দুর্ভোগে | আমার দেশ

প্রতিনিধি, শরীয়তপুর প্রকাশ : ২৭ ডিসেম্বর ২০২৫, ০৯: ৫০ প্রতিনিধি, শরীয়তপুর অর্থসংকট, জমি অধিগ্রহণ জটিলতা ও প্রশাসনিক অচলাবস্থায় পাঁচ বছর ধরে থমকে আছে চাঁদপুর-শরীয়তপুর সড়কের উন্নয়নকাজ। দেশের দক্ষিণ ও দক্ষিণ-পশ্চিমাঞ্চলের ২১টি জেলার মানুষ দুর্ভোগের শিকা


The ‘1 Nojor’ media platform is now live in beta, inviting users to explore and provide feedback as we continue to refine the experience.